
The future of Coral Bay came into the spotlight once again when the Senate Committee of the Whole met Tuesday to consider a modified permit and a lease for submerged land for a controversial 144-slip marina on St. John.
The Senate committee called to testify the principal owners of Summerโs End Group, LLC along with their consultants, attorneys and supporting members of the community to make their best case for moving the marina forward.
Senators repeatedly acknowledged that the developersโ arguments were compelling: A marina would bring much-needed revenue to the territory suffering from the effects of twin hurricanes in 2017 and the current COVID-19 pandemic; the marinaโs sewage pump-out facilities would address a long-standing problem with waste disposal in the harbor; and a marina would provide entrepreneurial opportunities for ancestral families who own property nearby.

As the hearing went on, however, several senators expressed misgivings with the process by which the permits were modified.
Senators questioned whether present economic and environmental conditions allow Governor Albert Bryan Jr. to bypass Coastal Zone Management processes and modify the permits now under consideration.
Some background about the projectโs permitting process is necessary to understand the present issue.
The St. John Committee of the Coastal Zone Managementย approved separate land and water use permits for the Summerโs End Marinaย (now also known as the St. John Marina) in 2014 after a contentious hearing.
Lawsuits and appeals followed.
In 2016, the Board of Land Use Appeals ruled that the permits should be consolidated since the land and water portions of the project would be interdependent and have cumulative impacts. However, their directive wasnโt implemented until January 2020.
Kenneth Mapp, who was governor at that time, opposed the project, and the approval process stalled. However, when Gov. Bryan took over in 2018, he took a renewed interest in the marina, and in 2019 he forwarded the permits to the Senate for ratification.
In anย October 2019 Senate Committee of the Whole hearing, senators found multiple reasons for not acting on the governorโs recommendation.
These included disputes with several landowners who leased property to Summerโs End Group; a lawsuit with a competing marina project; and a change in ownership of two sizable pieces of property (13A and 13B Estate Carolina,) making them unavailable to the marina developers.
The change in ownership required major changes in the projectโs design, which many say should have resulted in the permits being sent back to the St. John Committee of Coastal Zone Management for approval.
In a December 2019 letter to the governor, Senate President Novelle Francis Jr. said the permit was โdefective,โ because โit was signed and issued unilaterally by the Chairman of the St. John Committee without a vote of approval or other involvement of the St. John Committee.โ
However, in January 2020,ย Gov. Bryan administratively consolidated the permitsย (as directed by the Board of Land Use Appeals in 2016) and sent them back to the Senate for ratification.
Now, six months later, expressing confusion over discrepancies on the permit before them, senators at Tuesdayโs hearing asked Coastal Zone Management Director Marlon Hibbert for clarification, since the Senateโs legal counsel was not available.
Hibbert said, โWe are not privy to the modifications you are considering now. We cannot provide an opinion on this. We approved the original permits. Thereโs no violation with them. We have not seen the modifications.โ
Upon further questioning, Vonetta Norman, an attorney with DPNR, said, โThe modification and consolidation were done under the governorโs independent power and not through the department.โ
Senators questioned whether the governorโs action was appropriate. Bryan sent the permit to the Senate under a provision for emergency enforcement power, 12 VIC, Sec. 911g of the Coastal Zone Management Act.
The statute states, โThe Governor may modify or revoke any coastal zone permit that includes development or occupancy of trust lands or submerged or filled lands approved pursuant to this section upon a written determination that such action is in the publicโs interest and that it is necessary to prevent significant environmental damage to coastal zone resources and to protect the public health, safety and general welfare.โ

Chaliese Summers, one of the principals of Summerโs End Group, LLC, testified that the territoryโs economic need โ along with the โdeplorableโ condition of the waters in Coral Bay harbor โ meet the conditions of the statute. Earlier in hearing, Summers said feces (presumably from unregulated boats) were found floating in the harbor; she could provide photographic proof.
Although senators agreed that the waters of the harbor needed remediation, some senators were not convinced that the governorโs actions were appropriate.

โThe process has become convoluted,โ said Sen. Janelle Sarauw. โIโm not against a marina, but itโs a question of process. As lawmakers we set precedents.โ Sarauw questioned the exclusion of the St. John Committee of CZM from the decision, and the use of Sec. 911g, which she termed the part โof the V.I. Code with the biggest loopholeโ to bring the permit before the Senate.
Sen. Kurt Vialet said senators shouldnโt rely on the governorโs interpretation of Sec. 911g.ย โWhy canโt we move forward and send the modification to the St. John Committee of Coastal Zone for their approval?โ
The answer to the question has to do with the makeup of the five-member committee; one of the members, David Silverman, has been a vocal opponent of the Summerโs End project. Vialet addressed the issue directly, saying that Silverman would not be able to vote on the permit because of a clear conflict of interest.
Vialet had other concerns with the use of Sec. 911g, which he said refers only to projects which are already fully permitted, โbut does not speak to one that hasnโt started.โ

Vialet also pointed out that if Sec. 911g was being adhered to, then technically the modified permit sent by the governor to the Senate in January would have been implemented already without the Senateโs approval; the statute states under emergency provisions it would have gone into effect in 30 days if the Senate didnโt act.
Vialet said he supports the project, but the Senateโs ratification would come back to haunt them if the approval isnโt done the right way.
Boyd Sprehn, an attorney for Summerโs End Group, said developers โwere trying to do things the right way.โ He told Vialet the U.S. Army Corps of Engineers, a federal agency that must also approve the project, is looking to see that the V.I. Legislature ratifies the project, showing community support. โYour approval precedes the U.S. Army Corps of Engineersโ approval,โ he said.
Earlier in the hearing, Katherine English, an attorney working on behalf of the developers, explained that changes in Army Corps personnel have led to delays in processing the Summerโs End marinaโs permit. A new USACE reviewer has recently come on board and is taking some time to become familiar with literally thousands of pages of documents, English said.
Senators also heard from Jeff Boyd, president of Marine Management and Consulting, who said that, in spite of the recession and the pandemic, the recreational boating industry is growing and a dozen other islands in the Caribbean are expanding existing facilities or building new ones.
David Cattie, another attorney working on behalf of Summerโs End Group, said that properties leased by Summerโs End that were under dispute last October are being resolved.
Cattie said agreements concerning parcels owned by the Marsh Sisters Trust are moving forward with the appointment of new trustees, and that the sale of another property (owned by Genoveva Rodriguez and Jim Phillips) to Summerโs End will soon take place. However, no representatives from any of these individuals testified at the Senate hearing on Tuesday.
Senators did get to hear from Samuel Rhymer, property manager for the Moravian Church V.I. Conference, which owns the land on which a competing marina is being developed.ย That project, known as Sirius or T-Rex, is planned for 11 acres across the harbor from the proposed site of the Summerโs End Marina.
Last October, Rhymer testified that the Summerโs End project would deprive them of the โfull and equitable use of their land for their own marina projectโ and damage the environment. At Tuesdayโs hearing, Rhymer said their concerns about Summerโs End are still pending in Superior Court.
โWe have been totally ignored by Summerโs End,โ Rhymer said. He characterized the move to consolidate the permit as โunfair and should be treated as illegal.โ
Sen. Donna Frett-Gregory questioned the Summerโs End Groupโs financing for the project. Summers said financing the $73 million project โhas always been the easy part. We have multiple funding sources; the permitting is what has held us up.โ Summers said the developers have already invested $4 million in the permitting process.
Frett-Gregory asked Summers to provide letters of financial interest by investors.
Towards the end of the six-hour hearing, Sen. Allison DaGazon compared the frustration she felt to her recent experience when the Senate considered legislation to legalize the recreational use of cannabis in the territory. โSomething is always missing,โ she said. โWe are the ones who vote yes or no on a process no one understands because we want progress.โ







