On all three islands there will be line striping, box cover repairs and/or asphalt restoration.
Owner: AT&T Mobility, USVI.
ISLAND: St. Thomas/St. John and St. Croix
Contractor: Bermudez Longo Diaz – Masso Inc.
Dates: August 23- 27, 2021
HOURS: 7a.m. to 5 p.m.; 7 p.m. to 6 a.m. (night work)
This project is expected to improve capacity, reliability, resiliency and increase performance of the existing communication network. Motorists can expect delays this week due to partial road closures while work is happening at the following locations:
St. Thomas
Box Cover Repairs and Asphalt Restoration:
- Sugar Estate Road
- Raphune Hill
- Weymouth Hwy
- Dronningens Gade
- Mafolie Road
- Hull Bay
- Norre Gade
- Taarneberg Gade
- Red Hood Road
- Crown Mountain
- Turpentine Run
- Mahogany Run
- Mariendahl Road
- Smith Bay Road
- Mandahl Road
- Donoe Bypass
- Wintberg
- Judy Gomez Hwy
- Magens Bay
- General Gade – 7 p.m. to 6 a.m.
- Waterfront – 7 p.m. to 6 a.m.
Line Striping:
- Raphune Hill
- Weymouth Rhymer Hwy
- Mafolie Road
- Sugar Estate Road
St. Croix
Line Striping
- Mon Bijou
- Centerline Road / Queen Mary Highway
- Canaan Ridge Road
St. John
Box Cover Repairs
- Centerline Road